Glamis

Glamis

Creating energy from the Lera Dam

Site Details

Glamis is another old mill site, water from the Lera Dam (pictured below) used to power a mill and also fed a fish hatchery. The intake and header tank wil be retrofitted to the existing dam, as shown in the drawing opposite. Some of the water from the loch will be diverted through a pipeline to a turbine in the old mill.

Electricity Output

The scheme will generate enough electricity to power 48 UK households.

System Elements

  • Rotating mesh screen
  • 850m of buried pipe
  • Available head 29m
  • Max. flow rate 400l/s
  • 57kW Cross-flow Turbine
  • Seasonal flow regime to protect fish

Status

Completed

GlamisWir GlamisIntake

GlamisTurbine